Alterations to the Gannochy Building

Value: £605,000.00

Services: Quantity Surveying Service & CDM Co-Ordinator Services

Project Description: Internal alterations and extension to create sports laboratories.  The works generally comprised of internal alterations and new build extension forming upper floor above existing foyer and offices

Falkirk Football Academy

Value: £690,000.00

Services: Quantity Surveying Service & CDM Co-Ordinator Services

Project Description: New build changing rooms and ancillary accommodation.  The works comprised of the construction of traditionally built two storey sports pavilion including provision of changing rooms, shower area, w/c’s, meeting rooms, storage etc.

Astro Hockey Pitch, Glenalmond College

Value: £290,000.00

Services: CDM Co-Ordinator Services

Project Description: Removal of the existing 3G synthetic grass carpet and installation of new synthetic carpet. 

Kings Park, Skate Park

Value: £80,000.00

Services: CDM Co-Ordinator Services

Project Description: Design and construction of a new skatepark facility including provision of associated equipment, landscaping works etc

Proposed 3G Sports Pitch Callander Leisure

Value: £520,000.00   

Services: CDM Co-Ordinator Services

Project Description: Replacement of the existing all weather sports pitches with a new 3G sports pitch.
The works generally included :

  • Removal of existing blaes pitch and sub-base,
  • Drainage
  • Installation of new 3G synthetic playing surface with associated line markings
  • Electrical works
  • Perimeter fencing
  • Floodlighting

Howe of Fife RFC

Value: £1,200,000.00

Services: Quantity Surveying Service & CDM Co-Ordinator

Area: 860m2

Project Description: Alterations and extension to the existing grandstand, changing rooms and storage to form new changing areas, function room, clubrooms, offices, and equipment storage.  The works comprised generally of the following:-

  • Downtakings to and stripping out of the existing building
  • Demolition of existing water tower and associated tank
  • Removal of asbestos cement roof to existing grandstand.
  • New concrete floor slab, masonry walls and structural steel frame and steel roof structure with metal cladding finish
  • Structural timber or metal holorib upper floor structure supporting concrete floor
  • Timber and metal internal partitions with plasterboard finish
  • Insulated metal wall cladding
  • Removal of all existing mechanical and electrical installations
  • New mechanical and electrical installations to suit new layouts
  • Ventilation installations
  • Formation and fitting out to bars and kitchens
  • Lift installation
  • Refurbishment and alterations to existing Stand area
  • External works
  • New drainage and mains services connections

 

Football Pitches, Peffermill

Value: £362,000.00

Services: Quantity Surveying Service

Area: 27 aches

Project Description: SFA Compliance Works to Grass Football Pitches at Peffermill Playing Fields.
The works involve but are not limited to:

  • Reorientation of pitches at East Pavilion to provide a full size SFA compliant pitch
  • New perimeter fencing
  • New spectator fencing
  • Floodlighting
  • General Pedestrian Lighting
  • Spectator Stands
  • Dugouts
  • Turnstiles
  • Pitch Formation Works
  • Drainage and Irrigation Works
  • Lining works
  • Associated electrical works
  • Re-location of cricket pitch